Establishing Outcomes-based Accountabilities

12 Steps Series – 7 of 12
Executive Summary
In many projects the accountability structure is optimised for work output, not business outcome.
At best, this shows up as delivery of output (solution and deliverables) but not necessarily the outcome. Worst case it shows up as “everyone owns it” language, blurred roles, duplicated support functions, and progress that looks busy but doesn’t move the needle.
The shift is simple (but not easy):
- Structure Outcome Accountabilities around Outcome → Problems → Results with named owners.
- Ensure that your Outcome Accountabilities are in place before your Work Breakdown Structure. (WBS).
- Work breakdown structure is essential — but it is subservient to the business outcome, not the other way around.
In other words, deliver like a swimming team, not a rugby team.
Swim Team vs Rugby Team:
The accountability you’re aiming for

Look at the swimmers in the pool.
They’re all in the same race, heading in the same direction, using the same pool. But each swimmer has a lane. That matters. Imagine if everyone simply jumped in together and agreed to “collaborate closely.” Plenty of effort. Plenty of splashing. Not much clarity about who is responsible for what.
Sometimes projects look like this. Everyone is contributing, everyone is involved, and everyone has a role — but the accountabilities overlap so much that it becomes difficult to tell who actually owns the result.
You see it when:
– Several people are accountable for the same thing
– Decisions require everyone to agree
– Responsibilities overlap between teams
– When something slips, ownership becomes a discussion
Collaboration is important, but blurred accountability isn’t collaboration.
A good swim team shares the same goal, coaches and support — but when the race starts, everyone knows their lane.
Projects should work the same way: shared Outcome, clear accountabilities.
When WBS is the Accountability Structure
“When accountability is based on the WBS,
Outcomes becomes a slogan on slide 2”
In many projects, accountability is based on how the work is packaged.
When Work Breakdown Structure (WBS) becomes the accountability structure, the outcome becomes a slogan on Slide 2 — impressive, laminated, and largely ceremonial.
Here are three common WBS patterns
(they’re common because they’re practical).
1) Phase / lifecycle-led accountability
(Design →Build →Test →Deploy)
This is the classic “we’ve got good governance” setup.
- You get strong ownership of phases.
- You get crisp status reporting.
- You also get handover theatre: “It’s with Test now.” (ie. It is no longer emotionally ours)
The hidden cost is that nobody is accountable for solving the problem end-to-end. They’re accountable for completing their phase. When the outcome isn’t achieved, everyone can still truthfully say they delivered. (Which is awkward, because they did.)
2) System / component-led accountability
(CRM / ERP / data platform / integration)
This one is especially seductive in tech-heavy programs.
- Work is broken into buildable components.
- Vendors and architects can plan cleanly.
- “80% build complete” becomes a comfort blanket.
But business outcomes tend to live between components: adoption, decision rights, process behaviour, measurement discipline. If accountability is split by component, those “between” spaces become nobody’s job. Benefits don’t fail loudly. They just… don’t arrive.
3) Vendor / contract package-led accountability
(Vendor A / Vendor B / SI / Internal)
This is the contract doing what it was designed to do: define deliverables.
- Accountability aligns to statements of work.
- Governance aligns to what is “in scope”.
- Progress aligns to what gets invoiced.
The failure mode is predictable: the contract is managed successfully while the program fails operationally. “Out of scope” becomes the de facto operating model. And outcomes can’t be escalated against a purchase order.
None of these structures are “wrong.” They are legitimate ways to organise work.
They just become dangerous when we let them become the accountability model for outcomes.
Traditional WBS is valid, the problem is the order of operations.
Outcome Accountabilities should come before Work Breakdown structure (WBS)
- Step 1. Assign Outcome Accountabilities:
What must change in the business?
Outcome → Problems → Results → Outcome Accountability Structure
- Step 2: Do your WBS:
What work will we do to make that change happen?
Deliverables, phases, tasks, vendors, components → Work Breakdown Structure
What Project Leaders Need to Do
You need to do three things before you can assign Outcome Accountabilities.
1. Define the Outcome (and actually agree it) – (see Headway Outcomes Step 2)
Not a fluffy statement. A measurable intent.
If your outcome statement can’t survive the question “how will we know?”, then it’s not agreed — it’s just politeness.
2. Break the Outcome into Problems – (see Headway Outcomes Step 3)
A Problem is something that must be solved for the outcome to happen.
This is where many teams accidentally drift back into WBS thinking.
3. Break each Problem into Results – (see Headway Outcomes Step 4)
A Result is the evidence that lets you say, “this problem is being solved.”
Results are where strategy stops sounding intelligent and starts becoming measurable.
– Not “training delivered” – But “capability demonstrated to X standard by Y cohort”
– Not “system deployed” – But “process cycle time reduced from A to B”
This is also where the line of sight: Outcome → Problem → Result becomes reality.
The Two Outcome Accountabilities
An Outcome Manager will already have been assigned from the very beginning (otherwise who’s running the show?!)
You might in fact be the Outcome Manager.
Anyway, the Outcome Manager, now needs to assign two distinct accountabilities.
1) Problem Managers
Problem Managers are accountable to the Outcome Manager.
They are like the Team Captain looking after the swim team.
They are accountable for ensuring their respective ‘Problems’ are solved.
In order for this to be true Result Managers need to deliver each of their ‘Results’
2) Result Managers
Result Managers are accountable to Problem Managers.
They are the actual swimmers in a swim team, each with their own respective lane.
They are accountable for ensuring their respective ‘Results’ are achieved.
Ask yourself …
Are we able to trace Outcome → Problems → Results — and name an owner for each?
Remember:
Your Outcome Accountability Structure and your Work Breakdown Structure (WBS) are not necessarily the same thing.
Outcome Accountabilities are focused on the required business outcomes
Delivery Accountabilities are focused on organising the delivery work required to make the outcomes happen.
They may overlap, and in some cases the same person may hold both an outcome accountability and a delivery accountability. But they do not have to.
Sometimes Problem and Result Managers are best placed embedded in the project running an actual workstream workstream. Sometimes they are not. Often, they are a business stakeholder with visibility across multiple workstreams who can see whether their Problem and Result Outcomes are actually coming together.
The discipline is not to force these structures apart. The discipline is to define them separately, then decide deliberately where and how they should connect.
Example – Outcome Accountabilities Structure